Battery Energy Storage
Systems for Cyprus
Utility-scale and C&I BESS — fully engineered and delivered. From 215 kWh C&I containers to 10 MW grid stations. Supply, installation, commissioning and lifetime O&M.
Complete BESS — Factory to Grid
Lighthief is Cyprus's dedicated BESS EPC contractor. We handle the full project lifecycle — equipment procurement direct from OEM, import logistics, civil works, electrical installation, DSO interface, commissioning and O&M.
- Direct OEM supply — Linyang Energy (integrator) + Kehua Tech (PCS)
- Utility-scale skid containers: 1 MW to 10 MW per station unit
- C&I containerised ESS: 215 kWh Deye MS-GS215 with integrated solar MPPT
- IEC 61850 / IEC 104 / Modbus — EAC/DSO ready from day one
- DisperonEMS cloud SCADA — real-time monitoring, trading integration
- 10-year cell warranty + LTSA contracts available
Utility-Scale & C&I Systems

BCS1250K-C-HUD T1
- AC Power1.0–1.25 MW
- DC Bus1000–1500 Vdc
- AC Output690 Vac 3-phase
- Transformer1,000–1,250 kVA
- Efficiency≥99%
- Grid CodeEN 50549-2 ✓

BCS2000K-C-HUD T2
- AC Power2.0–2.5 MW
- PCS Units2 × BCS1000K or BCS1250K
- TransformerSL-2000 (2,000 kVA)
- Container20ft Std (6,058 mm)
- Efficiency≥99%
- CommsIEC 61850 / Modbus

BCS4000K-C-HUD T4
- AC Power4.0–5.0 MW
- PCS Units4 × BCS1000/1250K
- Transformer4,000–5,000 kVA
- Container40ft HC (12,192 mm)
- IP RatingIP65
- CorrosionC5 coastal grade

BCS10000K-C-HUD T8
- AC Power8.0–10.0 MW
- PCS Units8 × BCS1000K or BCS1250K
- Transformer10,000 kVA
- MV Output22 kV (custom)
- Container40ft HC (12,192 mm)
- SLD22 kV available ✓
What BESS Does for You
Grid Services & Frequency Regulation
Earn revenue providing FCR, balancing energy and voltage support to the TSO/DSO. Response time <200 ms via IEC 104 dispatch command.
Solar Firming & Curtailment Recovery
Store excess daytime solar, dispatch at evening peak or on grid request. Eliminates curtailment losses and maximises PPA revenue for co-located PV.
Energy Arbitrage
Charge during low-price hours, discharge at peak. DisperonEMS integrates with day-ahead and intraday market data to optimise cycles automatically.
C&I Peak Shaving
Reduce maximum demand charges for commercial buildings, hotels and factories. Deye MS-GS215 with on-site PV delivers 24/7 reliability and bill savings.
Island Mode & Microgrid
Full off-grid and islanded operation for remote sites. Generator integration (STS, dry contacts) included as standard — no additional inverter required.
DSO Connection & Compliance
EAC (Cyprus) grid connection from day one. IEC 61850, IEC 104, Modbus pre-configured. EN 50549-2 TÜV certified — no additional grid study delays.
Fully Certified Stack
EN 50549-2
Grid connection — TÜV certified PCS
IEC 62477-1
PCS safety — CB certificate
IEC 61850
Substation communication & control
IEC 104
Telecontrol / SCADA protocol
CE-LVD & CE-EMC
Low voltage & EMC directives
IEC 62619
Battery safety — stationary applications
UL 9540A
Fire propagation — cell & pack level
IP65 · C5
Outdoor & coastal environment rated
Your BESS Partner in Cyprus
Direct OEM Access
Factory-direct from Linyang Energy and Kehua Tech — no middlemen, no mark-up chains. OEM pricing with full traceability and warranty assignment.
DisperonEMS — Our Own Platform
Proprietary cloud SCADA built for Linyang/Kehua hardware. Real-time telemetry, market integration, remote dispatch and alarms — no third-party licence fees.
Full DSO & Grid Interface
We prepare and submit EAC connection applications, protection relay settings and IEC 104 SCADA point lists on your behalf. Grid connection from day one.
Cyprus-Based EPC Team
Local engineers, subcontractors and DSO relationships. EAC permits, crane logistics and customs clearance — 28 parks already delivered across 5 districts.
Lifetime O&M Coverage
LTSA contracts from commissioning. Linyang-backed 10-year battery warranty. On-site preventive maintenance, remote diagnostics and spares logistics included.
215 kWh to 100+ MWh
C&I Deye systems for commercial premises; Linyang containers for utility scale. One contractor, one contract, any capacity. Multi-site portfolio management available.
From Enquiry to Energisation
Site Assessment
Load profile, grid connection point, civil survey, DSO pre-application
Technical Design
System sizing, SLD, protection settings, BOM finalisation
Contract & Order
EPC contract, OEM purchase order, EAC permit submission
Delivery & Install
Factory production (~90 days), sea freight, crane installation, cabling
Commission & O&M
OEM commissioning team, DSO energisation, DisperonEMS go-live, LTSA start
Ready to deploy battery storage?
Tell us your site location, required capacity and application. We'll respond with a preliminary technical proposal within 5 working days.